Division: Blue Star Atlantic
Client: Schweppes Australia Pty Ltd
Completion: Jan-2015
Description: The SP15 Project delivered the Schweppes Goodna site with additional LV supply capacity in order to facilitate the installation of a new bottle manufacturing line and latest technology water bottling line which can produce both spring and sparkling water products. The works included the upgrade of LV supply to the site via the supply and installation of a new Energex substation, new 2500A consumers mains, new MSB and associated sub main cabling and distribution switchboards, equipment control panels and MCC’s.